How the estimate is built
Instead of one price per square foot, the calculator works out the materials the job really needs and prices them, then adds labor:
- Pavers: area plus pattern waste × price per sq ft.
- Gravel base: depth from the project and soil (patio 4"–6", driveway 8"–12"), extended 6" past the edges, plus 20% for compaction, converted to tons at 1.4 t/cu yd.
- Bedding sand: 1" layer plus 10%; polymeric sand from the joint volume of 4" × 8" pavers; edging on edges not against the house.
- Haul-away: excavation (base + sand + paver thickness) over the base area, × 1.25 because dug soil swells.
- Labor: per sq ft by project type, or your rate.
Estimates for common sizes
Concrete pavers, running bond, well-drained soil, soil hauled away, default prices.
| Project | Low | Typical | High | Typical per sq ft |
|---|---|---|---|---|
| 10 × 10 ft patio | $1,511 | $2,069 | $3,036 | $20.69 |
| 12 × 16 ft patio | $2,831 | $3,902 | $5,759 | $20.32 |
| 20 × 20 ft patio | $5,802 | $8,032 | $11,902 | $20.08 |
| 3 × 30 ft walkway | $1,593 | $2,095 | $3,056 | $23.28 |
| 12 × 24 ft driveway | $5,412 | $7,306 | $10,380 | $25.37 |
| 20 × 24 ft driveway | $8,872 | $12,028 | $17,152 | $25.06 |
Assumptions
| Labor per sq ft | Low | Typical | High |
|---|---|---|---|
| patio | $8.00 | $12.00 | $18.00 |
| walkway | $9.00 | $13.00 | $20.00 |
| driveway | $10.00 | $15.00 | $22.00 |
| Pavers per sq ft | Low | Typical | High |
|---|---|---|---|
| Concrete pavers | $3.00 | $4.50 | $8.00 |
| Clay brick pavers | $4.00 | $6.00 | $10.00 |
| Natural stone (flagstone, travertine, bluestone) | $6.00 | $12.00 | $25.00 |
| Permeable concrete pavers | $5.00 | $7.00 | $12.00 |
Sealing: $1.00–$3.00 per sq ft. Bulk material prices (base $45/ton, sand $50/ton, polymeric sand $30/bag, edging $20 per 8 ft piece, haul-away $35 per cu yd) are editable defaults: delivery fees and regional prices vary widely. These ranges are planning assumptions, not quotes. For the quantities alone, use the paver calculator.
Ask each contractor for base depth, compaction method, edge restraint type and whether haul-away is included. A low bid with a 2" base is not the same job as a 6" base.